4346-4659
Manual for filling 23 Key points in ISU Billing System and Monthly Compliance from April 25 onwards
29-03-2025
2
4243-79
Action required for timely upload and processing of short assessed amounts
24-03-2025
3
1129-1281
Internal Audit of Accounts of HPSEBL for the Financial year 2024-25(1st Half Year)
08-11-2024
4
947-1100
Internal Audit of Accounts of HPSEBL for the Financial Year 2024-2025(1st Half Year)
26-10-2024
5
2090-2125
Revision of Pension and Family Pension of Pre 01.01.2016 Pensioners /Family Pensioners
04-10-2024
6
227-45
Corrigendum for internal audit parties have been deputed for conducting internal audit of HPSEBL for FY 2023-24(3rd & 4th Qtr) and Sr.no.5
04-05-2024
7
66-215
Internal Audit of Accounts of HPSEBL for the financial year 2023-2024(3rd & 4th Qtr/Half Yearly)
02-05-2024
8
13-15
Special Drive for review/settlement of works audit reports/paras
02-04-2024
9
1498-1643
Internal Audit of Accounts of HPSEBL for financial year 2023-24(1st and 2nd Qtr/Half yearly)
17-11-2023
10
3483-3732
Quarterly Review Note on the Internal Audit of Consumers Accounts (w.e.f 01.04.2023 to 30.06.2023) i.e Ist Quarter of FY 2023-24
21-10-2023
11
2395-2639
Maintaining of Sundry Charges & Allowances Register as per the provisions of sales manual instruction No.279
07-08-2023
12
2266-2616
Quarterly Review Note on the Internal Audit of Consumers (w.e.f 01.01.2023 to 31.03.2023) 4th quarter of FY 2022-23
27-07-2023
13
555-914
Quarterly Review Note on the Internal Audit of Consumers Accounts (w.e.f. 01.10.22 to 31.12.22
24-05-2023
14
142-291
Internal Audit of Accounts of HPSEBL for the financial year 2022-23(4th Qtr.)
04-05-2023
15
4591-98
Tour Programme of Work Audit party No-1
20-03-2023
16
10313-10672
Quarterly Review Note on the Internal Audit of Consumers accounts (w.e.f.01.07.22 to 30.09.22) i.e. as 2nd Quarter. of FY 22-23
31-01-2023
17
4302-4400
Internal Audit of Accounts of HPSEBL for the Financial Year 22-23 (3rd Qtr.)
21-01-2023
18
3977-83
Tour Programme of Work Audit Party No.1 (Field) w.e.f 12.12.22 to 21.01.23 to conduct work audits of Electrical System Circle & Division
21-12-2022
19
6905-7105
Regarding submission of service books for vetting
16-12-2022
20
3557-67
Tour programme of Works Audit Party No.II
31-10-2022
21
3410-3550
Internal Audit of Accounts of HPSEBL for the financial year 22-23 (2nd Qtr.)
29-10-2022
22
8287-8646
Quarterly review note on the internal audit of consumers(w.e.f. 01.04.22 to 30.6.22)1st qtr. of FY 22-23
21-10-2022
23
3352-62
Tour Programme of works audit party No.1
13-10-2022
24
1549-1689
Internal Audit of Accounts of HPSEBL for the financial year 22-23 (1st Qtr.)
06-08-2022
25
5100-5459
Quarterly review not on the internal audit of consumers accounts (01.01.22-31.03.22) 4th qtr of FY 21-22
02-08-2022
26
1013-26
Tour Programme of works Audit Party No.-1
18-06-2022
27
1006-12
Tour programme of Works Audit Party No.II
17-06-2022
28
840-939
Special Audit to find out as to whether EPF & ESIC subcriptioins are being deposited
19-05-2022
29
496-633
Internal Audit of Accounts of HPSEBL for the Financial Year 2021-22 (4th Qtr.)
07-05-2022
30
439-52
Tour Programme of works Audit Party No. II
23-04-2022
31
428-35
Non-Implementation of SAP (ERP) in Generation wing
22-04-2022
32
383-427
Postponed of Tour programme
20-04-2022
33
222-359
Internal Audit of Accounts of HPSEBL for the financial year 2021-22 (4th Qtr.)
13-04-2022
34
62-187
Internal Audit of Accounts of HPSEBL, for the financial year 21-22 (4th Qtr.)
06-04-2022
35
35-393
Quarterly review note on the internal audit of consumers accounts (w.e.f. 01.07.21-30.9.21) 2nd quarter
04-04-2022
36
22-32
Tour Programme of Works Audit Party No. II
01-04-2022
37
3321-29
Non-Implementation of SAP (ERP) in Generation wing
26-03-2022
38
678-85
HPSEBL outstanding Inspection Comments and Details of Para
04-03-2022
39
3198-3205
Transfer & Posting of Sh.Rajwant Negi JAO(Account) posted in WAP to WAP Field-II (Camp at PR&ALDC-Totu ) with immediate effect
28-02-2022
40
3163-74
Tour Programme of Works Audit Party No.1
23-02-2022
41
7172-7530
Quarterly review note on the internal audit of consumers accounts(w.e.f 01.04.2021 to 30.06.2021) 1st Qtr
19-02-2022
42
2844-51
To direct Sh.Layak Ram Sr.Asstt.to report his duty in WAP-Field II(Camp at PR&ALDC Totu Shimla ) with immediate effect
15-02-2022
43
2852-55
Tour Programme of Works Audit Party No. II
15-02-2022
44
912-19
HPSEBL outstanding Inspection Comments and Details of Para
08-02-2022
45
2598-2635
Acceptance of telephone bill through e-bill on E-mail ID & mobile no audit observation thereof
02-02-2022
46
6879-81
Physical Verification of Store's
01-02-2022
47
6819-26
100% Physical verification report of store under ED Una
28-01-2022
48
2371-79
Tour Programme of works Audit Party No.2
13-01-2022
49
2355-64
Tour Programme of works Audit Party No.1
12-01-2022
50
848-55
Details of Outstanding Inspection Notes and Paras
05-01-2022
51
4629-5078
HPSEBL Review Note on the Internal Audit of Consumers Accounts
31-12-2021
52
4446-49
Physical verification of Store
16-12-2021
53
2040-49
Work Audit paras are still pending
13-12-2021
54
817-24
Details of outstanding inspection notes and charges
09-12-2021
55
4244-46
Physical Verification of Store's
04-12-2021
56
1894-1903
Tour Programme of Works Audit Party No.II
20-11-2021
57
1871-82
Internal Audit tour Programme for the FY-2021-22
12-11-2021
58
1855-63
Tour programme of Works Audit Party No.1
11-11-2021
59
740-47
Details of outstanding inspection observations and paras of HPSEBL
10-11-2021
60
1774-1805
Internal audit of Accounts of HPSEBL for the Financial Year 2021-22 upto Sep2021
01-11-2021
61
3804-07
Physical Verification of Store
29-10-2021
62
1756-62
Tour Programme of Work Audit Party No-II
26-10-2021
63
1722-32
Tour programme of Works Audit Party No.1
18-10-2021
64
685-92
HPSEBL Audit paras Information
05-10-2021
65
2287-89
Physical verification of store
04-10-2021
66
2284-86
Physical verification of store
04-10-2021
67
2281-83
Physical Verification of Store
04-10-2021
68
1409-1568
Internal audit of Accounts of HPSEBL for the financial year 2021-22
01-10-2021
69
1406-08
Regarding non-submission of compliance of internal audit report by Sr.Xen ED No-II Shimla for financial year 2020-21
01-10-2021
70
1578
Regarding non-submission of compliance of internal audit report by O/o CE(Comm) for the FY 2020-21
01-10-2021
71
1399-99
Regarding non-submission of compliance of internal audit report by Sr.EE ED Chopal for the FY 2020-21
01-10-2021
72
1400-02
Regarding non-submission of compliance of internal audit report by Sr.EE ED Theog for the FY 2020-21
01-10-2021
73
1580
Regarding non-submission of compliance of internal audit report from O/O CE(MM) Shimla for the FY 2020-21
01-10-2021
74
1403-05
Regarding non-submission of compliance of internal audit report by Sr.EE ED Sunni for the FY 2020-21
01-10-2021
75
1569-71
Regarding non-submission of compliance of internal audit report by Sr.EE ED-I Shimla for the FY 2020-21
01-10-2021
76
1572-74
Regarding non-submission of compliance of internal audit report by Sr.EE ED City Shimla for the FY 2020-21
01-10-2021
77
1579
Regarding non-submission of compliance of internal audit report by O/O CE(P&M) for the FY 2020-21
01-10-2021
78
1582-83
Regarding non-submission of compliance of internal audit report by Sr.EE Arki for the FY 2020-21
01-10-2021
79
1584-85
Regarding non-submission of compliance of internal audit report by Sr.EE ED Parwanoo for the FY 2020-21
01-10-2021
80
1586-87
Regarding non-submission of compliance of internal audit report by Sr.EE ED Nalagarh for the FY 2020-21
01-10-2021
81
1588-89
Regarding non-submission of compliance of internal audit report by Sr.EE ED Solan for the FY 2020-21
01-10-2021
82
1590-91
Regarding non-submission of compliance of internal audit report by Sr.EE ED Manali for the FY 2020-21
01-10-2021
83
1594-95
Regarding non-submission of compliance of internal audit report by Sr.EE ED Keylong for the FY 2020-21
01-10-2021
84
1596-97
Regarding non-submission of compliance of internal audit report by Sr.EE ED Kullu for the FY 2020-21
01-10-2021
85
1598-99
Regarding non-submission of compliance of internal audit report by Sr.EE ED Thalout for the FY 2020-21
01-10-2021
86
1600-01
Regarding non-submission of compliance of internal audit report by Sr.EE ED Reckongpeo for the FY 2020-21
01-10-2021
87
1602-03
Regarding non-submission of compliance of internal audit report by Sr.EE ED Rampur for the FY 2020-21
01-10-2021
88
1604-05
Regarding non-submission of compliance of internal audit report by Sr.EE ED Kaza for the FY 2020-21
01-10-2021
89
1606-07
Regarding non-submission of compliance of internal audit report by Sr.EE ED Rohru for the FY 2020-21
01-10-2021
90
1608-09
Regarding non-submission of compliance of internal audit report by Sr.EE ED Jubbal for the FY 2020-21
01-10-2021
91
1610-12
Regarding non-submission of compliance of internal audit report by Sr.EE ED Jawali for the FY 2020-21
01-10-2021
92
1613-15
Regarding non-submission of compliance of internal audit report by Sr.EE ED Nurpur for the FY 2020-21
01-10-2021
93
1616-18
Regarding non-submission of compliance of internal audit report by Sr.EE Dalhousie for the FY 2020-21
01-10-2021
94
1616
Regarding non-submission of compliance of internal audit report by Sr.EE ED Ghumarwin for the FY 2020-21
01-10-2021
95
1619-21
Regarding non-submission of compliance of internal audit report by Sr.EE ED Chamba for the FY 2020-21
01-10-2021
96
1619
Regarding non-submission of compliance of internal audit report by Sr.EE M&T Division Solan for the FY 2020-21
01-10-2021
97
1622-23
Regarding non-submission of compliance of internal audit report by Sr.EE M&T Division Kangra for the FY 2020-21
01-10-2021
98
1622-24
Regarding non-submission of compliance of internal audit report by Sr.EE ED Fatehpur for the FY 2020-21
01-10-2021
99
1624-27
Regarding non-submission of compliance of internal audit report by Sr.EE ED Paonta Sahib for the FY 2020-21
01-10-2021
100
1625-27
Regarding non-submission of compliance of internal audit report by Sr.EE ED Killar for the FY 2020-21
01-10-2021
101
1628-29
Regarding non-submission of compliance of internal audit report by Sr.EE ED Nadaun for the FY 2020-21
01-10-2021
102
1628-31
Regarding non-submission of compliance of internal audit report by Sr.EE ED Nahan for the FY 2020-21
01-10-2021
103
1630-31
Regarding non-submission of compliance of internal audit report by Sr.EE ED Hamirpur for the FY 2020-21
01-10-2021
104
1632-33
Regarding non-submission of compliance of internal audit report by Sr.EE ED Barsar for the FY 2020-21
01-10-2021
105
1634-35
Regarding non-submission of compliance of internal audit report by Sr.EE ED Amb for the FY 2020-21
01-10-2021
106
1636-37
Regarding non-submission of compliance of internal audit report by Sr.EE ED Una for the FY 2020-21
01-10-2021
107
1638-39
Regarding non-submission of compliance of internal audit report by Sr.EE ED Gagret for the FY 2020-21
01-10-2021
108
1640-41
Regarding non-submission of compliance of internal audit report by Sr.EE ED Sarkaghat for the FY 2020-21
01-10-2021
109
1642-43
Regarding non-submission of compliance of internal audit report by Sr.EE ED Dharampur for the FY 2020-21
01-10-2021
110
1644-45
Regarding non-submission of compliance of internal audit report by Sr.EE ED Gohar for the FY 2020-21
01-10-2021
111
1646-47
Regarding non-submission of compliance of internal audit report by Sr.EE ED Mandi for the FY 2020-21
01-10-2021
112
1648-49
Regarding non-submission of compliance of internal audit report by Sr.EE ED Jogindernagar for the FY 2020-21
01-10-2021
113
1650-52
Regarding non-submission of compliance of internal audit report by Sr.EE ED Shahpur for the FY 2020-21
01-10-2021
114
1653-55
Regarding non-submission of compliance of internal audit report by Sr.EE ED lambagaon for the FY 2020-21
01-10-2021
115
1656-58
Regarding non-submission of compliance of internal audit report by Sr.EE ED Dehra for the FY 2020-21
01-10-2021
116
1659-61
Regarding non-submission of compliance of internal audit report by Sr.EE ED Baijnath for the FY 2020-21
01-10-2021
117
1662-64
Regarding non-submission of compliance of internal audit report by Sr.EE ED Palampur for the FY 2020-21
01-10-2021
118
1665-67
Regarding non-submission of compliance of internal audit report by Sr.EE ED Kangra for the FY 2020-21
01-10-2021
119
1668-69
Regarding non-submission of compliance of internal audit report by Sr.EE ED Kotla Jeori for the FY 2020-21
01-10-2021
120
1670-71
Regarding non-submission of compliance of internal audit report by Sr.EE Electrical System Division Bijni mandi for the FY 2020-21
01-10-2021
121
1672-73
Regarding non-submission of compliance of internal audit report by Sr.EE Electrical System Division Nalagarh for the FY 2020-21
01-10-2021
122
1674-75
Regarding non-submission of compliance of internal audit report by Sr.EE Electrical System Division Nahan for the FY 2020-21
01-10-2021
123
1676-77
Regarding non-submission of compliance of internal audit report by Sr.EE Electrical System Division Totu Shimla for the FY 2020-21
01-10-2021
124
1678-79
Regarding non-submission of compliance of internal audit report by Sr.EE Electrical System Division Solan for the FY 2020-21
01-10-2021
125
1680-81
Regarding non-submission of compliance of internal audit report by Sr.EE Electrical System Division Kunihar for the FY 2020-21
01-10-2021
126
1682-83
Regarding non-submission of compliance of internal audit report by Sr.EE Electrical System Division Babha Nagar for the FY 2020-21
01-10-2021
127
1684
Regarding non-submission of compliance of internal audit report by O/O CE(ES) for the FY 2020-21(upto Sep.2020)
01-10-2021
128
1685-86
Regarding non-submission of compliance of internal audit report by RE Khauli P/H Division Shahpur for the FY 2020-21
01-10-2021
129
1687-88
Regarding non-submission of compliance of internal audit report by RE Giri P/H Division Giri Nagar Nahan for the FY 2020-21
01-10-2021
130
1689-90
Regarding non-submission of compliance of internal audit report by RE Andhra P/H Division Chirgaon for the FY 2020-21
01-10-2021
131
1691-92
Regarding non-submission of compliance of internal audit report by RE Larji P/H Division Thalout Mandi for the FY 2020-21
01-10-2021
132
1693-94
Regarding non-submission of compliance of internal audit report by RE Ghanvi P/H Division Jeori for the FY 2020-21
01-10-2021
133
1695-96
Regarding non-submission of compliance of internal audit report by RE P/H Division Bhabha Nagar for the FY 2020-21
01-10-2021
134
1697-98
Regarding non-submission of compliance of internal audit report by Sr.Xen P/H Division TCD Pandoh for the FY 2020-21
01-10-2021
135
1699-70
Regarding non-submission of compliance of internal audit report by RE Binwa P/H Division Utralla for the FY 2020-21
01-10-2021
136
1702-03
Regarding non-submission of compliance of internal audit report by Sr.XEN PLCC Sundernagar for the FY 2020-21
01-10-2021
137
1704-05
Regarding non-submission of compliance of internal audit report by SE(PR&ALDC) Totu Shimla for the FY 2020-21
01-10-2021
138
1706-07
Regarding non-submission of compliance of internal audit report by Sr.Xen RCD Mandi for the FY 2020-21
01-10-2021
139
1708-09
Regarding non-submission of compliance of internal audit report by Sr.Xen GCD Jeori for the FY 2020-21
01-10-2021
140
1710-12
Regarding non-submission of compliance of internal audit report by Sr.Xen ED Karsog for the FY 2020-21
01-10-2021
141
1713-15
Regarding non-submission of compliance of internal audit report by Sr.Xen ED Sundernagar for the FY 2020-21
01-10-2021
142
1581
Regarding non-submission of compliance of internal audit report by O/o Sr.EE(MTC) Division Shimla for the FY 2020-21
01-10-2021
143
1590.91
Regarding non-submission of compliance of internal audit report by Sr.Xen ED Baddi for the FY 2020-21
01-10-2021
144
1577
Regarding non-submission of compliance of internal audit report by O/o CE(SP) Shimla for the FY 2020-21
01-10-2021
145
1575
Regarding non-submission of compliance of internal audit report by AO(Admin) F&A Wing Shimla for the FY 2020-21
01-10-2021
146
1339-1348
Tour Programme of Works Audit Party No.1
24-09-2021
147
1281-96
Tour Programme of Works Audit Party No-II
17-09-2021
148
1188-1204
Tour Programme of Works Audit Party No.II
14-09-2021
149
1034-50
Tour programme of works Audit Party No.II
07-09-2021
150
606-13
Audit Paras Information
04-09-2021
Powered by HPSEBL